Commissioning date confirmed

There has been a delay in commissioning caused by a fault on the sub sea cable between Oban and Mull. SSE hope to complete the repair of this fault by 13 May and have given us a date of 20 May for connecting Garmony to the National Grid! All our suppliers and contractors are now preparing for this date and we are hoping to have a final G59 certificate on 2 June – which means we can then export power onto the grid and register with Ofgem for full accreditation for our Feed in Tariff.

Here are a few photos of the turbine house and also of a visit from Derek Mackay MSP, minister for Transport and the Islands.