SSE remove grid constraint

MICT have just had formal confirmation from SSE that our offer of a grid connection is now free of constraint (at Taynuilt). Previously, their offer was based on the condition that the timing of the resolution of the constraint and the potential cost to us was unspecified – not a very helpful offer! We are… Continue reading SSE remove grid constraint

Logo for GEM

We have launched a competition between local schools to design a logo for the project. The holding and operating company called Green Energy Mull (GEM) and the logo will incorporate the new name.

Planning Granted

Just a quick update of progress.Things are going pretty well with lots of work behind the scenes at the moment. Planning permission has been granted for the project and our application to Forestry Commission has also been successful. We understand that the licence from Scottish Environmental Protection Agency will also be granted shortly.Because of restrictions on… Continue reading Planning Granted

Results

And the result is….1650 people voted YES53 people voted NO2 blank papers96.7% of those who voted are in favour.70.6% turnout.68.3% of the electoral roll are in favour.Thanks to everyone who voted and to all those people who helped to promote the ballot to get such a high turnout rate. 70.6% is a massive compliment to… Continue reading Results